Floating Demonstrator Installation & Recovery

Project Summary

TADEK delivered integrated engineering, analysis, and offshore execution support for the installation and recovery of the BPT Demonstrator at FabTest.

Our team developed a novel tow and mooring approach, enabling safe installation, stable operations, and controlled recovery over a three-month offshore testing campaign.

The Challenge

The installation presented a series of critical engineering and operational constraints:

  • Complex and heavy mooring installation with low-cost assets
  • Limited deck clearance required development of alternative chain handling solutions
  • Vessel and equipment limitations impacting installation methodology
  • Late-stage changes driven by spot market availability and operational constraints

TADEK‘s Role

Tadek delivered end-to-end engineering, analysis, and offshore support across all project phases:

  • Bollard pull, hookup, and installation sensitivity analyses
  • FEED support and installation strategy development
  • Vessel and equipment specification and procurement
  • Steelwork and supporting structural design
  • Operational procedures and QHSE documentation
  • On-site engineering oversight and stakeholder coordination

Our Approach

Engineering was iteratively developed and refined to address constraints and maintain operability offshore:

  • Early stage optioneering and steering to improve constructability
  • Performed analysis to validate novel tow, hookup, and mooring configurations
  • Adapted procedures and engineering documentation to accommodate vessel change within 24 hours
  • Integrated offshore feedback into engineering decisions to maintain safe and workable operations

Outcomes

Installation and recovery were completed safely and on time:

  • Engineering solutions enabled installation without modification to existing vessel pipework
  • Alternative chain handling method allowed safe execution under constrained conditions
  • Vessel change accommodated without disruption to overall project delivery
  • Installation and recovery executed with full engineering oversight and control

 

YEAR

2024 - 2025

REGION

Cornwall, United Kingdom

MARKET

Renewables